
Payment Claims and Reference Dates - back to the future
Thursday, 11 February 2010
Courtesy of DLA Phillips Fox, Brisbane
The recent decision of Tenix Alliance Pty Ltd v Magaldi Power Pty
Ltd [2010] Qsc 7 has seen a return to the reasoning that payment
claims under the Building and Construction Industry Payments Act 2004
(Qld) can be made any time ‘on’ and ‘after’ the entitlement
to claim arises.
In our November 2009 Construction Update, we reported on the
implications of the Supreme Court of Queensland’s decision in Reed
Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd [2009] QSC
345. In that decision the Court held that claimants under the
Building and Construction Industry Payments Act 2004 (Qld) (BCIP Act)
were entitled to issue a payment claim only ‘on’ the reference
date.
The view of the Court in Reed Constructions (Qld) Pty Ltd v
Martinek Holdings Pty Ltd was contrary to previous decisions of
courts in other jurisdictions, particularly New South Wales, that
payment claims can be made ‘from’ each reference date even where
the construction contract requires that payment claims are to be made
‘on’ a particular day or date.
In this update we look at the subsequent decision of the Supreme
Court of Queensland in Tenix Alliance Pty Ltd v Magaldi Power Pty Ltd
[2010] QSC 7 (Tenix v Magaldi) which takes a different tack to Reed
Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd in regard to
when a payment claim can be made.
The decision also clarifies other important issues concerning the
operation of the BCIP Act.
Calculation of a Reference Date
The BCIP Act provides that a ‘reference date’ under a
construction contract, means— ‘(a) a date stated in, or worked
out under, the contract as the date on which a claim for a progress
payment may be made for construction work carried out or undertaken
to be carried out, or related goods and services supplied or
undertaken to be supplied, under the contract; or (b) if the contract
does not provide for the matter—
(I) the last day of the named month in
which the construction work was first carried out, or the related
goods and services were first supplied, under the contract; and
(ii) the last day of each later named
month.’ Other relevant provisions of the BCIP Act that concern
‘reference dates’ provide: Section 12, Rights to progress
payments, which provides that ‘from’ each reference date under a
construction contract, a person is entitled to a progress payment a
claimant cannot serve more than one payment claim for each reference
date under the construction contract.
It was in consideration of these provisions and in particular that
two payment claims cannot be made in respect of the one reference
date that led the court in Reed Constructions (Qld) Pty Ltd v
Martinek Holdings Pty Ltd to hold that a payment claim must be given
‘on’ the reference date.
In Tenix v Magaldi, the Court agreed that the BCIP Act does not
permit two claims to be made in respect of the one reference date but
held that this does not mean the BCIP Act does not permit a payment
claim to be made ‘after’ the relevant reference date. The Court
then held that under section 12 of the BCIP Act, a payment claim can
be made ‘on or after’ the reference date.
What Does this mean?
There are now two Supreme Court of Queensland decisions with
differing views on whether a payment claim can be given after a
reference date.
Given the previous court decisions in New South Wales, although
not binding in Queensland, and the express words of section 12 of the
BCIP Act that a payment claim can be given ‘from’ each reference
date, the better view is that a payment claim can be given after the
reference date.
However, until a further decision of the Court is made on this
issue, a prudent claimant should, whenever possible and particularly
when the contract requires a payment claim to be given ‘on’ a
reference date, ensure the payment claim is given on that date.
Other Issues of Interest
The Court in Tenix v Magaldi was also asked to determine a number
of other issues associated with the operation of the BCIP Act of
interest to both claimants and respondents:
What constitutes stating an amount
proposed to be paid in the payment schedule.
Whether a payment claim can include a
claim for delay costs.
Whether a payment claim can include
claims for amounts to be incurred after the date of the payment
claim.
Whether the inclusion of a claim for an
amount without any entitlement in the payment claim is sufficient to
invalidate the whole claim.
Amount proposed to be paid The respondent in Tenix v Magaldi
stated in its payment schedule that certain amounts would be paid
provided the claimant agreed to certain conditions.
The respondent submitted that the amount stated was an amount that
it was willing to negotiate but not what they were prepared to pay
and therefore, by imposing conditions, the payment schedule
effectively stated nothing would be paid.
However, the Court stated that it could equally be read that the
amount stated would be paid if the conditions were satisfied and
therefore the payment schedule could not be read as either a
statement that nothing will be paid or as a statement that an amount
will be paid.
In those circumstances, the Court held that the payment schedule
did not comply with the requirements of section 18(2)(b) of the BCIP
Act and was invalid.
Delay costs
The payment claim included a claim for delay costs. The
respondent argued that such costs were not a valid claim.
Under the BCIP Act, a payment claim is defined as a payment ‘for’
construction work. Generally the word ‘for’ is to be given a
wide meaning. In Tenix v Magaldi the Court held that the meaning of
‘for’ is wide enough to include a claim for delay costs as
construction work.
Claims for delays for periods after the date of the claim The
payment claim also included a claim for delay for periods subsequent
to the date of the payment claim.
The Court held that such a claim was not in reality a claim ‘for’
construction work and given that the claim for delay included costs
to be incurred in the future, that portion after the date of the
claim, was too remote to be a claim ‘for’ construction work
carried out.
That part of the delay claim for periods after the date of the
payment claim was excised by the Court from the claim.
Part of the payment claim incorrect The effect of the issues
discussed above meant that the Court found that:
The payment claim was valid.
The payment schedule was invalid.
The claimant was entitled to judgment for the amount of the claim,
including delay costs up to the date of the payment claim.
This publication is intended as a first point of reference and
should not be relied on as a substitute for professional advice.
Specialist legal advice should always be sought in relation to any
particular circumstances and no liability will be accepted for any
losses incurred by those relying solely on this publication.
The claim for delay costs which at the time of the claim had not
occurred was not within the meaning of ‘construction work’ under
the BCIP Act and that part of the payment claim was invalid.
Implications
The Court’s decision in Tenix v Magaldi provides some strong
guidance for both claimants and respondents wishing to either take
advantage of the payment regime in the BCIP Act or protect themselves
from exposure to unwarranted payments, including: To be very aware of
the provisions of the contract as to when payment claims can be made.
Claimants should still prudently ensure, if required under the
construction contract, that payment claims are submitted ‘on’ the
reference date.
Respondents should not rely on a payment claim submitted after the
reference date being invalid but should ensure a payment schedule is
provided.
Respondents should not place any conditions on the amount that
they propose to pay in the payment schedule. If payment is disputed,
to ensure a valid payment schedule is provided, it is better to say
the scheduled amount is nil and provide reasons for withholding
payment.
Negotiations to pay some amounts on conditions can be held
separate from the BCIP Act process if required.
Claimants can include delay costs in a payment claim but only if
there is a relevant provision in the contract entitling payment for
delay but not for delay costs after the date of the payment claim.
A court may be prepared to separate parts of a payment claim that
are not valid and calculate the valid amount that is to be paid.
Note: This article is a general commentary on a recent case. It is not legal advice. If you want legal advice on your particular matter, please contact DLA Phillips Fox. If you want to know more about the operation of the BCIPA and security of payment or want to apply for an adjudication, please contact AIQSANA.
|